SB 684 & SB 1123 Eligibility Checklist
Determine if your land qualifies for ministerial approval for up to 10 units
Last Updated: January 2026
I. The "Killer" Exclusions (Pass/Fail)
If any of these apply, the site is likely INELIGIBLE.
-
Fire Risk: Located in a "Very High Fire Hazard Severity Zone" (VHFHSZ).
-
Tenant Occupancy: Currently occupied by a tenant, or occupied at any point in the last 5 years.
-
Rent Control / Affordability: Subject to any form of rent control, price controls, or deed-restricted affordability.
-
Ellis Act: Tenants were evicted via the Ellis Act in the last 15 years.
-
Wetlands: Located within a designated wetland.
-
Habitat: Habitat for protected or endangered species.
-
Conservation: Under a conservation easement.
-
Farmland: Designated as "Prime Farmland" or "Farmland of Statewide Importance."
-
Hazardous Waste: Listed on the "Cortese List" (hazardous waste site).
-
Earthquake Zone: In a delineated earthquake fault zone (unless compliant with seismic codes).
-
Flood Zone: In a FEMA 100-year floodplain (unless FEMA-compliant improvements are made).
II. Zoning Path (Select One)
You must meet ALL criteria in one of the paths below.
Path A: Multifamily (SB 684)
- Zoned for Multifamily (R-2, R-3, R-4) or Mixed-Use
- Lot size: 5 acres or less
- Can be vacant or developed (subject to demo rules)
- New lots must be at least 600 sq. ft.
Path B: Single-Family (SB 1123)
- Zoned for Single-Family (R-1)
- Lot size: 1.5 acres or less
- Can have "remanant" house we block off.
- New lots must be at least 1,200 sq. ft.
III. Project Design Constraints
The proposed project must adhere to these limits.
-
Unit Count: Total of 10 or fewer residential units.
-
Lot Count: Total of 10 or fewer subdivided parcels.
-
Unit Size: Average floor area does not exceed 1,750 net habitable sq. ft. per unit.
-
Urban Location: Lot is within an incorporated city or Census-designated urbanized area.
-
Infill Status: At least 75% of the site's perimeter adjoins developed urban uses.
-
Density Requirement:
- If site is in Housing Element: Build at least the density projected by the City.
- If NOT in Housing Element: Build at least 66% of max allowable density (or 20 units/acre, whichever is lower).
IV. Civil Considerations
Potential civil engineering costs to factor into your feasibility analysis.
1. Frontage Requirements (Public Street Work)
-
Underground overhead lines along entire frontage? ($1,500 - $2,500 / LF)
-
Remove utility pole on property? ($5k - $15k)
-
Is pole a "Junction Pole" (wires in 3+ directions)? ($50k - $100k+)
-
Can we pay "In-Lieu Fees" instead? ($10k - $30k)
-
Install new city-standard street light? ($15k - $25k)
2. Wet Utilities (Water & Sewer)
-
Extend sewer main (>200ft away)? ($40k - $80k)
-
Install new public fire hydrant (nearest >300ft)? ($30k - $50k)
3. Public Right-of-Way (Streets, Curbs & Driveways)
-
New driveway curb cut? ($8k - $12k)
-
Close/demolish unused driveway curb cut? ($4k - $6k)
-
Relocate utility box/guy wire for driveway? ($15k - $30k)
-
Install new "Type G" concrete curb & gutter? ($75 - $110 / LF)
-
Option to use "AC Dike" (asphalt berm) instead? ($15 - $25 / LF)
-
"Slot pave" (asphalt patch) next to new curb? ($25 - $40 / LF)
-
Fix cracked curb/gutter on existing frontage? ($100 - $150 / LF)
-
Install or replace non-compliant sidewalks? ($15 - $25 / SF)
-
Grind and overlay street asphalt (half-width)? ($8 - $12 / SF)
-
Protect or remove existing street trees? ($3k - $5k / tree)
4. Stormwater & Grading
-
Create >2,500 SF impervious surface (triggers PDP)? ($25k - $40k)
-
"Net export" site (more cut than fill)? ($40 - $75 / CY)
-
Hard rock/conglomerate soil (requires breakers)? ($100 - $150 / CY)
-
Retaining walls >3ft high (masonry)? ($45 - $65 / SF)
-
Curb outlet/catch basin for drainage? ($5k - $15k)
5. Soft Costs (Civil Specific)
-
Storm Water Quality Management Plan (SWQMP)? ($5k - $10k)